Donnerstag, 29. August 2013

Hard-core brutalism and temporary mollification

Most of the brutalist concrete work is in place in the garden, along the edge of the brook.  The individual elements have now been put together along with the big steps/bench above the rain-water pool.

Three segments of retaining wall sequence with rain-water pool and steps/bench in place

We still need the steps between the wall sections to be placed, and the front/drop edge of the pool to have its camber inverted - don't ask.

Donnerstag, 22. August 2013

Possible stone walls

We are looking at styles of rocks for the curving wall around the courtyard.  Two are left in the race, basalt from Roßdorf and granite from Groß Bieberau.

Roßdorf wall build with nice dark stone

Possible wall style, but not the right colour

Montag, 19. August 2013

Arrival of pool

After the lull of the summer holidays and the excitement of the Ortskernfest, there are some things happening at the building site again.

The window maker has started installing the frames.  Six are in and the rest should follow this week.  The glass parts will come next week.  Hopefully.

The electrician has been preparing light switch locations and sockets ... yesterday I had to say how high to put the switches for the bedside lights above the floor (60 cm).

Outside, the retaining walls have all been poured and the shuttering is off.

Three sections of the retaining wall

Other parts of the concrete for the garden have been delivered including the rain-water pool.  Maybe they will get installed this week.

Rain-water pool ready for deployment by retaining wall sequence